A $130 million project to reconstruct irrigation infrastructure in Surkhandarya, Kashkadarya, Bukhara and Namangan regions with the participation of China Eximbank has been put on hold after Chinese contractors proposed significantly higher prices. Water Resources Minister Shavkat Khamraev said this during a Government Hour session at the Legislative Chamber of the Oliy Majlis on November 11.

The minister was responding to a question from Imomnazar Tursunov, a member of the parliamentary faction of the People’s Democratic Party of Uzbekistan. According to the MP, information provided by the ministry showed that work had not started on several projects scheduled for implementation in 2026.

Tursunov said no funds had been disbursed for the $130 million irrigation project involving China Eximbank, a $37 million project to modernise 95 pumping stations, or a $5 million project with the participation of the European Bank for Reconstruction and Development (EBRD) to modernise 110 pumping stations.

In response, Khamraev explained that Chinese companies had initially been expected to start work using their own funds, with the costs later reimbursed through concessional loans from China.

“When we held negotiations with these companies, they submitted documents proposing prices that were not just 10% or 20% higher, but more than twice as high. We negotiated for over a year but failed to reach an agreement,” the minister said.

The government subsequently approached China and opted to seek a concessional loan from China Eximbank. According to Khamraev, the bank spent six months reviewing and assessing the project before proposing at least three companies as potential contractors. This process took another year.

CITIC won the tender, but its bid was also 20% above the expected cost. After negotiations to reduce the price failed, the ministry began talks with Sinohydro, which had placed second in the tender.

“If we rush to complete this work at an inflated price, the budget will ultimately have to cover the difference. That is why the project is on hold,” Khamraev said.

The minister said the programme would take at least two years. He pledged that canals would be properly lined with concrete in 2027−2028, based on projects that had passed the required expert review.

Khamraev also said that loans obtained under state guarantees through foreign investment exceeded the ministry’s own budget allocations. According to him, the ministry has a dedicated centre for managing foreign investment and a deputy minister responsible for these matters.